Instruction Manual
106-300NFX Rev. 4.2
January 2002
2-24 Installation Rosemount Analytical Inc. A Division of Emerson Process Management
World Class 3000
1. Run the line voltage through the bulk-
head fitting on the bottom of the MPS
where marked LINE IN, Figure 2-18.
Refer to Figure 2-19. Connect the line
voltage to the LINE IN terminal on the
MPS terminal board located inside the
unit. Tighten the cord grips to provide
strain relief.
2. The MPS can accommodate up to four
probes. The terminal strips on the MPS
termination board are marked PROBE
1, PROBE 2, PROBE 3, and PROBE 4.
Select PROBE 1 if this is the first probe
and electronic package installed on the
MPS.
3. Make the connections from the MPS to
the IFT as shown in Figure 2-19. Run
wires from the MPS Termination Board
inside the unit through the bulkhead fit-
ting on the bottom of the unit where
marked SIGNAL IN, Figure 2-18. After
the connections are made, tighten the
cord grips to provide strain relief.
NOTE
!
Upon completing installation, make sure that the probe is turned on and operating
prior to firing up the combustion process. Damage can result from having a cold
probe exposed to the process gases.
During outages, and if possible, leave all probes running to prevent condensation and
premature aging from thermal cycling.
If the ducts will be washed down during outage, MAKE SURE to power down the
probes and remove them from the wash area.